PROJECT DETAILS
Client:
Bournville Village Trust
Value:
£30,000
Specification:
Re-establish a 30m length of Hay Green Stream by excavating embankments and laying stone gabions, removing old footbridge and installing new. Regrading embankments as part of the completion process.
Site preparation:
Removal of vegetation, roots, trees. Stank (dam) upstream and pump through works whilst working on site
WORKS
- Demolish and remove existing footbridge and replace with new.
- Excavate embankment and stream bed to a width of 3m
- Install and fill mattresses with gabion stone
- Regrade all embankments and fill with topsoil
- Repair and make good all fencing and surrounds